5.1

Identify overall need for housing support services including owner occupiers

1,3

Needs assessment exercise

Lead

Timescale

Resources

Progress Indicator

SPT

April 2004

Within existing SPT resources

Needs assessment exercise complete

No.

Action

Objective

Outputs

5.2

Expend number of services providing support at home

1,3,5

Number of services increasing

Lead

Timescale

Resources

Progress Indicator

SPT

April 2006

Within existing SPT resources

No. of service providers/users

No.

Action

Objective

Outputs

5.3

Increase numbers of older people receiving high support packages.

3

Numbers receiving high support packages increasing

Lead

Timescale

Resources

Progress Indicator

SWD

April 2004

Within existing SPT resources

Numbers receiving high support packages increased by at least 40 per year

No.

Action

Objective

Outputs

5.4

Increase availability of community alarms

3

Numbers receiving community alarms increasing

Lead

Timescale

Resources

Progress Indicator

SWD

April 2004

Within existing SPT resources

Numbers receiving community alarms increased by at least 100 per year.

No.

Action

Objective

Outputs

5.5

Develop 24 very sheltered housing places in Motherwell

3

24 very sheltered housing places

Lead

Timescale

Resources

Progress Indicator

HPS/RSL/SPT

June 2004

SE Pipeline

Development complete

No.

Action

Objective

Outputs

5.6

Develop 27 very sheltered housing places in Cumbernauld

3

27 very sheltered housing places

Lead

Timescale

Resources

Progress Indicator

HPS/RSL/SPT

February 2004

SE Pipeline

Development complete

No.

Action

Objective

Outputs

5.7

Reconfigure local authority sheltered housing support services to better meet needs

3

Reconfigured services

Lead

Timescale

Resources

Progress Indicator

HPS

April 2004 - 2005

Within existing SPT resources

No. of service users

No.

Action

Objective

Outputs

5.8

Introduce a range of 'SMART technology' to assist the provision of support to people in their own homes

3

'SMART technology' introduced

Lead

Timescale

Resources

Progress Indicator

SPT

October 2004

SE Pipeline

No. of units with 'SMART technology'